The project envisages replacement of existing NGL Pipelines between Asab-Bab, Bab-Ruwais and Bu Hasa-MP 21 (Total 230 KM) in order to improve the integrity of the overall pipeline system as well as to provide for the anticipated additional production from the proposed new SGD Project.
Engineering, Procurement, Construction and Commissioning (EPC) Contract for the project was awarded to Dodsal in Nov’ 2007 and the project is planned for completion by April 2010. The project scope also includes demolition of existing pipelines after commissioning of all new pipelines.