  • Habshan - 3
  • Ruwais 3rd NGL Train
  • Asab - 2
  • Habshan - 4
  • Offshore Associated Gas Project (OAG)
  • Replacement of NGL Pipelines
  • Bu Has – Habshan Gas Pipeline (EPC)
  • Nitrogen Generation and Injection Projects
  • Natural Gas
  • Habshan Flare Gas Recovery Project


  • Projects Under FEED / EPC Bidding Stage
  • Integrated Gas Development Project (IGD)
  • Shah Gas Development Project (SGD)
  • Asab, Bab, Bu Hasa and Ruwais
      Modifications (ABBR)
  • Habshan Gas Development Phase 3 (Habshan - 3)

    Habshan 3 Project is designed to process 1,300 MMSCFD of condensate rich gas (Thamama "F") at Habshan and to produce 11,800 TPD NGL (including 3,400 TPD Ethane) and 130,000 BPD Condensate. Residue gas will be re-injected back into the reservoir for pressure maintenance purposes (gas cycling).

    Main facilities include two (2) trains each of Inlet Separation, Condensate Stabilization, Gas Treatment and NGL Recovery units. The project also includes installation of a Gas Re-injection System and a separate NGL Pipeline from Habshan to Ruwais, apart from various Utilities and Offsite facilities.

    EPC Contract for Habshan 3 Project was awarded to M/S Bechtel (UK) in Dec' 2004 and the facilities are in the final stages of construction are planned to be pre-commissioned and commissioned progressively by 2nd Qr.2009.