The project envisages transporting the compressed and dehydrated offshore associated gas from Das Island through a 200 KM long 30" offshore / onshore pipeline and to process it at the existing facilities in Habshan. It will establish a strategic link between the offshore and onshore facilities as well as reduce HSE risk due to congestion in Das Island.
The project is being implemented through 3 distinct EPC Packages covering Das Island Facilities (Package-1), Offshore Pipeline Facilities (Package-2) and Onshore Pipeline & Habshan Facilities (Package-3).
While EPC Package 1 is under implementation by ADGAS, Package-2 and Package-3 facilities are being executed by GASCO.
EPC Contracts for Pkg-2 and Pkg-3 were awarded to NPCC in Sept’2006 and Feb’2007 respectively and the facilities are planned to be ready for commissioning progressively by 1st Qr.2010, matching with the EPC completion of Package 1 facilities would also match.